Mulberry Place

Location: New Romney
Developer: Pentland Homes
Value: £7.5 million

The Project

Appointed by Pentland Homes on a £7.5 million groundworks contract. We completed the full groundworks first and second phase to build 170 2-4 bedroom houses.

Summary of works

  • Working with Natural England and Clients Ecology Consultants in response to on site reptile management
  • Laying car park etc. for main site accommodation
  • Laying all groundworks in the formation of the main sales unit later reinstating
  • 278 works, in road widening and junction reconfiguring along country lane adjacent to the developments entrance
  • Excessive surface water management control attenuation, in forming a series of oversize drainage discharging into large swales at the perimeter the site
  • Bulk excavation, cut and fill throughout the site
  • Piling and precast groundbeams to all units
  • Site is part of Romney Marsh and as such, groundwater strategy had to be put in place during the course of the works to minimise the effect to deep excavations
  • Deep drainage
  • Installing standard precast concrete block and beam floors
  • All main services
  • All estate roads and main access road, including KCC specification street lighting
  • All external paving’s surrounding the units grading, importing and laying topsoil
  • Grading, topsoiling and laying out the public open spaces, including paths

Let's Work Together